Project Spotlight: I-10 pavement project completed near Bowie

Contributed Photo/Courtesy ADOT: Drivers now have a smoother ride on Interstate 10 west of Bowie after the Arizona Department of Transportation completed a resurfacing project in Southern Arizona.

Twelve miles of pavement improved between mileposts 345-357

BOWIE – Drivers now have a smoother ride on Interstate 10 west of Bowie after the Arizona Department of Transportation completed a resurfacing project in Southern Arizona.

The $21 million project, which began in March, upgraded the widely used stretch of I-10 between mileposts 345-357. Crews removed the top layer of pavement on I-10 and replaced it with fresh asphalt to improve the driving surface. Work also included repairing existing bridge decks and box culverts, improving both safety and ride quality. 

Rumble strips, new pavement markings, and other related work were also completed within the project zone.

To limit traffic impacts, crews avoided full closures of I-10 and maintained one lane of travel in each direction during construction. 

Contributed Photo/Courtesy ADOT: A worker lays down fresh asphalt.

This 12-mile segment of I-10 carries an average of 21,000 drivers each day, making it a key commerce corridor in the Southwest. This project will ensure each of those drivers has an improved experience, and it’s one of many ways ADOT works to connect people and empower Arizona’s economy.